| Wireless Implemenatation Plan Timeline | Start | Finish |
| Complete Contract with WAN/LAN | 3/14/06 8:00 | 3/27/06 17:00 |
| Develop Support Plan for Students | 3/6/06 8:00 | 8/18/06 17:00 |
| Develop Network Access Rules | 3/22/06 8:00 | 6/13/06 17:00 |
| Map out Cable pathways | 3/13/06 8:00 | 3/31/06 17:00 |
| Equipment Purchase Req. | 4/3/06 8:00 | 4/21/06 17:00 |
| Get 3 quotes for pathway and cable install | 4/3/06 8:00 | 4/14/06 17:00 |
| Obtain approval on pathway install contract | 4/17/06 8:00 | 4/19/06 17:00 |
| Cable Pathway Installation | 4/20/06 8:00 | 5/31/06 17:00 |
| Delivery of equipment Mgmt system and Aps | 4/24/06 8:00 | 5/5/06 17:00 |
| Installation of Mgmt System and a few AP s to support the initial test | 4/24/06 8:00 | 5/26/06 17:00 |
| Work with IS Team to customize Login Screen for FHDA | 4/24/06 8:00 | 5/12/06 17:00 |
| Install AP's for Phase I; start w/ Beta test site | 4/17/06 8:00 | 5/26/06 17:00 |
| Beta Test Phase I | 5/29/06 8:00 | 7/7/06 17:00 |
| Following Successful Beta Test Activate remaining Phase I AP s bldg by bldg | 7/10/06 8:00 | 8/18/06 17:00 |
| Tune System: On Going | 5/26/06 8:00 | 5/26/06 17:00 |