Wireless Implementation Timeline


Wireless Implemenatation Plan Timeline Start Finish
Complete Contract with WAN/LAN 3/14/06 8:00 3/27/06 17:00
Develop Support Plan for Students 3/6/06 8:00 8/18/06 17:00
Develop Network Access Rules 3/22/06 8:00 6/13/06 17:00
Map out Cable pathways 3/13/06 8:00 3/31/06 17:00
Equipment Purchase Req. 4/3/06 8:00 4/21/06 17:00
Get 3 quotes for pathway and cable install 4/3/06 8:00 4/14/06 17:00
Obtain approval on pathway install contract 4/17/06 8:00 4/19/06 17:00
Cable Pathway Installation 4/20/06 8:00 5/31/06 17:00
Delivery of equipment Mgmt system and Aps 4/24/06 8:00 5/5/06 17:00
Installation of Mgmt System and a few AP s to support the initial test 4/24/06 8:00 5/26/06 17:00
Work with IS Team to customize Login Screen for FHDA 4/24/06 8:00 5/12/06 17:00
Install AP's for Phase I; start w/ Beta test site 4/17/06 8:00 5/26/06 17:00
Beta Test Phase I 5/29/06 8:00 7/7/06 17:00
Following Successful Beta Test Activate remaining Phase I AP s bldg by bldg 7/10/06 8:00 8/18/06 17:00
Tune System: On Going 5/26/06 8:00 5/26/06 17:00